Scheduling with Communication Delays via LP Hierarchies and Clustering

Abstract

We consider the classic problem of scheduling jobs with precedence constraints on identical machines to minimize makespan, in the presence of communication delays. In this setting, denoted by $\mathsf{P} \mid \mathsf{prec}, c \mid C_{\mathsf{max}}$, if two dependent jobs are scheduled on different machines, then at least $c$ units of time must pass between their executions. Despite its relevance to many applications, this model remains one of the most poorly understood in scheduling theory. Even for a special case where an unlimited number of machines is available, the best known approximation ratio is $2/3 \cdot (c+1)$, whereas Graham's greedy list scheduling algorithm already gives a $(c+1)$-approximation in that setting. An outstanding open problem in the top-10 list by Schuurman and Woeginger and its recent update by Bansal asks whether there exists a constant-factor approximation algorithm. In this work we give a polynomial-time $O(\log c \cdot \log m)$-approximation algorithm for this problem, where $m$ is the number of machines and $c$ is the communication delay. Our approach is based on a Sherali-Adams lift of a linear programming relaxation and a randomized clustering of the semimetric space induced by this lift.

Explore related subjects

Keep this discovery

BibTeXRIS

Sami Davies, Janardhan Kulkarni, Thomas Rothvoss, Jakub Tarnawski, Yihao Zhang. 2020-04-21. Scheduling with Communication Delays via LP Hierarchies and Clustering. https://arxiv.org/abs/2004.09682

Cite the original work for its findings. Save a collection to share your selection of sources.

KEEP EXPLORING

Related papers

Quasi-Monte Carlo Beyond Hardy-Krause II: $(1 + \varepsilon)n$ Samples Suffice

Numerical integration studies how well one can estimate the integral of a function $f$ over $[0,1)^d$ using $n$ sample points. The two classical methods, Monte Carlo (MC) and quasi-Monte Carlo (QMC), have complementary strengths and weaknesses, and a fundamental question is to design an approach that combines the benefits of both. Recently, building on the transference principle in discrepancy theory, Bansal and Jiang~\cite{BJ25a} gave a randomized QMC method that bridges MC and QMC guarantees using only i.i.d.\ samples. Their method also goes beyond the classical Koksma--Hlawka inequality: it achieves integration error $\widetilde{O}_d(\sigma_{\mathsf{SO}}(f)/n)$, where the smoothed-out variation $\sigma_{\mathsf{SO}}(f)$ can be substantially smaller than the Hardy--Krause variation that governs the classical bound. However, their algorithm requires $n^2$ i.i.d.\ samples as input, and this quadratic blowup is inherent to any method based on the transference principle. In this work, we bypass the quadratic blowup: for any constant $\varepsilon > 0$, we show that $(1+\varepsilon)n$ i.i.d.\ samples suffice to both obtain the beyond-Hardy--Krause guarantee of~\cite{BJ25a}, resolving an open problem posed there, and to produce low-discrepancy point sequences. Our algorithms are variants of the online Haar-thinning method of Dwivedi, Feldheim, Gurel-Gurevich, and Ramdas~\cite{DFG+19}.

cs.DS

Single-Exponential Algorithms and a Polynomial Kernel for Strong Connectivity Augmentation

Strong Connectivity Augmentation (SCA) asks whether a directed acyclic graph can be made strongly connected by adding at most $k$ prescribed links whose total weight is within a given budget. Klinkby, Misra, and Saurabh (SODA 2021) gave an $O^*(2^{O(k\log k)})$-time algorithm and asked whether the problem admits a single-exponential parameterized algorithm and a polynomial kernel. We answer both questions affirmatively: SCA can be solved in $O^*(9^k)$ time and admits a polynomial kernel with $O(k^4)$ vertices and $O(k^{16})$ bits. For unweighted SCA, we obtain $O^*(4^k)$ time and a kernel with $O(k^3)$ vertices. Our algorithms are based on a particularly simple reduction to Strongly Connected Spanning Subgraph with two edge costs.

cs.DS